CRMS4_IU_CM_PROCESS - UI Process Messages
The following messages are stored in message class CRMS4_IU_CM_PROCESS: UI Process Messages.
It is part of development package CRMS4_IU_CM_PROCESS_FRAMEWORK in software component CRM-S4-IU. This development package consists of objects that can be grouped under "S4CRM-IS Utilities: Sales Contract Processes".
It is part of development package CRMS4_IU_CM_PROCESS_FRAMEWORK in software component CRM-S4-IU. This development package consists of objects that can be grouped under "S4CRM-IS Utilities: Sales Contract Processes".
Message Nr ▲ | Message Text |
|---|---|
| 001 | Assertion failed &1. |
| 002 | Internal error &1. |
| 003 | &1&2&3&4 |
| 004 | &1&2&3&4. |
| 005 | &1: Process step for ID "&2" not found. |
| 006 | &1: Process step for key "&2" not found. |
| 007 | Process "&1" |
| 008 | Step "&1" |
| 009 | Requirement "&1" |
| 010 | &1: Requirement definition contains errors. |
| 011 | &1: Step definition contains errors. |
| 012 | &1: No active step found. |
| 013 | &1: Entry for mandatory field "&2" missing. |
| 014 | &1: Save not possible. |
| 015 | &1: An error occurred while saving. |
| 016 | Process "&1" not assigned to business role "&2". |
| 017 | Please choose a point of delivery. |
| 018 | Please choose a contract account. |
| 019 | Please choose a product. |
| 020 | No installation found for point of delivery &1 in premise &2. |
| 021 | More then 1 installation assigned to point of delivery &1 in premise &2. |
| 022 | Choose 'Force move-out' if the point of delivery is occupied. |
| 023 | Forced move-out was performed successfully. |
| 024 | Move-out document &1 created. |
| 025 | Move-out was performed successfully. |
| 026 | Move-out date must not be earlier than the move-in date. |
| 027 | No contract item found for contract &1. |
| 028 | Forced move-out could not be performed. |
| 029 | Move-out could not be performed. |
| 030 | Please choose a premise. |
| 031 | You are operating on the same premise from which the move-out is made. |
| 032 | Process "&1" is not possible for contract items with state: &2. |
| 033 | &1 is not possible for this contract item. |
| 034 | Process "&1" cannot be started without a confirmed business partner. |
| 035 | Process "&1" cannot be started without a confirmed premise. |
| 036 | Process "&1" is not possible. Contract item has already ended. |
| 037 | Forced move-out not possible. A move-in already exists on that date. |
| 038 | Point of delivery already occupied in the future. |
| 039 | No period items for sales contract item &1 found. |
| 040 | New move-in date must not be earlier than move-in date of old contract. |
| 041 | Copying the configuration failed. |
| 042 | Sales contract &1 for business partner is locked. |
| 043 | Move-in could not be performed. |
| 044 | Move-in document &1 created. |
| 045 | Move-in was performed successfully. |
| 046 | Product change date must not be the same as or earlier than move-in date. |
| 047 | Forced move-out not possible. A move-out date already exists. |
| 048 | Please choose a point of delivery with a valid installation. |
| 049 | Point of delivery &1 in premise &2 not found. |
| 050 | No product found for division &1. |
| 051 | Product division not the same as point of delivery division &1. |
| 052 | Step &1 is complete |
| 053 | Error: &1&2&3&4 |
| 054 | Warning: &1&2&3&4 |
| 055 | &1 can only be performed for contract items with the status 'Released'. |
| 056 | The selected point of delivery is not valid on the selected date. |
| 057 | Process "&1" is not possible. End date &2 later than retention date &3. |
| 058 | Completion for contract item could not be performed. Complete item '&1'. |
| 059 | Unable to save utilities sales contract &1. |
| 060 | No valid start and end date for utilities sales contract item &1. |
| 061 | Too many contracts found for installation &1 from &2 to &3. |
| 062 | Too many sales contract items for contract &1 from &2 to &3. |
| 063 | Execution of process &1 failed. |
| 064 | Product integration failed (&1). |
| 065 | &1: Specification for parameter "&2" is missing. |
| 066 | &1: &2 for key "&3" not found. |
| 067 | &1: No &2 could be determined. |
| 068 | &1: Move-out for the underlying utilities contract &2 is already done. |
| 069 | Starting PF process "&1" (&2). |
| 070 | Ending PF process "&1" with status "&2". |
| 071 | Suspending PF process "&1" in step "&2" with status "&3". |
| 072 | Resuming PF process "&1". |
| 073 | Execute step "&1". |
| 074 | Step "&1" failed! |
| 075 | Step "&1" is not implemented or missing friend IF_CRMS4_IU_CM_PF_PROCESS! |
| 076 | Process "&1" is not possible for contract with state: &2. |
| 077 | Process "&1" is not possible for contract item with state: &2. |
| 078 | Process "&1" is not possible for contract period with state: &2. |
| 079 | Step "&1" will be undone. |
| 080 | Step "&1" could not be undone. |
| 081 | &1 was executed successfully. |
| 082 | &1 failed. |
| 083 | &1: Contract item &2 is not the last. Last contract item is &3. |
| 084 | &1: Data of contract item &2 and utilities contract &3 are different. |
| 085 | &1: Inconsistency between util. sales contract &2 and IS-UT contract &3. |
| 086 | &1: Contract item &2 has already ended. |
| 087 | &1: Business partner &2 is blocked. |
| 088 | &1: Confirmed business partner is missing. |
| 089 | &1: Confirmed premise is missing. |
| 090 | &1: Sales contract &2 is locked. |
| 091 | Installation &1 is occupied and the forced move out flag is not set. |
| 092 | Move-in document &1 was reversed. |
| 093 | Move-out document &1 was reversed. |
| 094 | No existing move-in document found for contract '&1'. |
| 095 | No existing move-out document found for contract '&1'. |
| 096 | &1: Sales contract item is missing. |
| 097 | &1: &2 is missing. |
| 098 | Setting up follow up process &1. |
| 099 | Exit undo steps from step &1. |
| 100 | Follow up�process &1 will be skipped because process was aborted. |
| 101 | Undoing the forced move-out performed by the new contract process. |
| 102 | The chosen date &3 is not in validity range from &1 to &2 for product &4. |
| 103 | &1: Move-in document &2 was already reversed. |
| 104 | &1: Originating process cannot be determined for the contract item &2. |
| 105 | &1: Originating process for contract item &2 has wrong process type &3. |
| 106 | &1: Contract item &2 has not been ended yet. |
| 107 | &1: Move-out document &2 was already reversed. |
| 108 | &1 will be continued in the background. |
| 109 | &1 was aborted successfully. |
| 110 | Abort of &1 failed. |
| 111 | Move-in date must not be later than the move-out date. |
| 112 | &1: No suspended process available for this item. |
| 113 | &1 is not possible. Start date is too close to the end date. |
| 114 | &1 is not executable. The product for this contract was not changed. |
| 115 | &1 is not executable. Execute this action for contract item with ID &2. |
| 116 | &1: New move-out date &2 must not be earlier than the move-in date &3. |
| 117 | &1: New move-out date &2 must be earlier than &3. |
| 118 | &1: New move-in date &2 must be before the move-out date &3. |
| 119 | &1 cannot be executed because you do not have sufficient authorization. |
| 120 | The point of delivery is already occupied for the selected date. |
| 121 | Move-out date must not be earlier than start date of the contract item. |
| 122 | &1: A move-in in the future for contract item &2 at &3 already exists. |
| 123 | &1 already executed on item &2. |
| 124 | Insufficient authorization to change the contract &1. |
| 125 | Product configuration contains an error in period item &1. |
| 126 | Sales contracts exist. Items in processing for contract &1 from &2 to &3. |
| 127 | Occupied contract item &1 starts on the same day &2. |
| 128 | Sales contract item &1 is currently being processed. |
| 129 | Integration process is currently not possible and will be canceled. |
| 130 | Integration process canceled due to an error. |
| 131 | Multiple sales contract items found. |
| 132 | Sales contract item &1 found. |
| 133 | No product in division &4 found for sales contract integration. |
| 134 | Start time: &1 |
| 135 | End time: &1 |
| 136 | Run time: &1 / &2 seconds / &3 microseconds |
| 137 | Application log was saved under object / sub-object "&1". |
| 138 | Error occurred obtaining the lowest contract key. |
| 139 | Contract management integration is not active. |
| 140 | Contract management integration is not active for division &1. |
| 141 | Integration process for contract &1 canceled due to an error. |
| 142 | Integration process for contract &1 successfully completed. |
| 143 | Product change date must not be the same as or later than move-out date. |
| 144 | There are still ongoing processes for this point of delivery. |
| 145 | &1 failed at step &2 in BAdI, see error log. |
| 146 | &1 damage control could not be set up. |
| 147 | &1 failed to undo step &2 in BAdI, see error log. |
| 148 | Point of delivery &1 is not valid on request date &2. |
| 149 | Ongoing processes still exist for point of delivery &1. |
| 150 | Occupancy state determination for point of delivery &1 failed. |
| 151 | Point of delivery &1 already occupied on a future date &2. |
| 152 | Point of delivery &1 already occupied on &2. |
| 153 | Forced move-out not possible. A move-in already exists on &1. |
| 154 | Forced move-out not possible. A move-out already exists on &1. |
| 155 | Contract item is being migrated and will be available again soon. |
| 156 | No rate category set for product &1, no product integration is called. |
| 157 | Please select contract items to perform &1. |
| 158 | Contract item &1 |
| 159 | &1 at &2 was executed successfully. |
| 160 | &1 at &2 failed. |
| 161 | &1 at &2 will be continued in background. |
| 162 | Unable to start process &1. |
| 163 | Executed successfully for &1 of &2 entries. |
| 164 | Will be continued in the background for &1 of &2 entries. |
| 165 | Failed for &1 of &2 entries. |
| 166 | No startable process available or selected. Please adjust the selection. |
| 167 | Process &1 is not multiple process-capable. |
| 168 | For process &1 no steps are defined. Incorrect process configuration. |
| 169 | Process could not be ended. Process status inconsistent. |
| 170 | Process could not be canceled. Process status inconsistent. |
| 171 | Product &3 in sales contract item &2 has no rate category set. |
| 172 | All contract items must have the same division. |
| 173 | &1 failed. No damage control could not be set up. |
| 174 | It has already been billed up to date &3. |
| 175 | &1: Restorable contract item for contract item &2 not found. |
| 176 | &1: Remaining contract item for contract item &2 not found. |
| 177 | &1 at &2 was aborted successfully. |
| 178 | Sequenced process &1 is starting. |
| 180 | No valid &2 found with divison &4. |
| 181 | &1 valid &2 found with divison &4. |
| 182 | &1 valid &2 found with divison &4. |
| 183 | More than &1 valid &2 found with divison &4. |
| 184 | Move-in date has been adjusted due to changed move-out date. |
| 185 | Move-in date has not been adjusted to changed move-out date. |
| 186 | Purchase date cannot be in the future. |
| 187 | New purchase date must not be earlier than purchase date of old contract. |
| 188 | Move-in date has been changed successfully to &1. |
| 189 | Move-out date has been changed successfully to &1. |
| 190 | Move-in date could not be changed. |
| 191 | Move-out date could not be changed. |
| 192 | Error ocurred while trying to start the Advanced Variant Configuration. |