DPR_ENTITY_LINK - Roles: Messages

The following messages are stored in message class DPR_ENTITY_LINK: Roles: Messages.
It is part of development package DEVELOPMENT_PROJECTS_TEAM in software component PPM-PRO-RES. This development package consists of objects that can be grouped under "Project Management - Team/Participants/Roles".
Message Nr
Message Text
002Work of task assignment is too high for available working time
003Task assignment: Finish is before start
004Target object for role is unknown
005Task assignment is not within the validity of the role
006Task assignment is not within the validity of the task
007Task assignment: Dates of role or resource and task do not match
008Task assignment: Work exceeds capacity of task
009Task assignment: Work exceeds capacity of resource
010Task assignment: Work exceeds capacity of role
011Work of task assignment initialized to remaining work of task
012Task assignment: Work initialized to remaining demand of role
013Task assignment: Work initialized to remaining availability of BP
014Task assignment: Error occurred when initializing work
015Dates for &1 have not been entered or are invalid
016Task assignment could not be created
Privacy Policy