DPR_TASK - Messages for Tasks
The following messages are stored in message class DPR_TASK: Messages for Tasks.
It is part of development package DEVELOPMENT_PROJECTS_TASK in software component PPM-PRO-STR. This development package consists of objects that can be grouped under "Project Management - Tasks".
It is part of development package DEVELOPMENT_PROJECTS_TASK in software component PPM-PRO-STR. This development package consists of objects that can be grouped under "Project Management - Tasks".
Message Nr ▲ | Message Text |
---|---|
001 | Select a valid task type |
002 | Select a valid unit |
004 | You cannot change the task type because the task has been released |
005 | You cannot change the obligatory indicator |
006 | You cannot change the approval-relevant indicator |
007 | You cannot change the process because the task has been released |
011 | &1 &2 has not been completed |
012 | Actual date is in the future |
013 | Original task no longer exists for mirrored task &1 |
014 | Project &1 is already a subproject for a different master task |
015 | 'Relevant for Approval' indicator cannot be set for task &1 |
016 | Project type &1 does not allow subtasks to be created |
017 | Subproject for task &1 no longer exists |
018 | You do not have authorization for original task &1 for mirrored task &2 |
019 | Cannot change tasks: Action &1 is not possible |
020 | Cannot change external tasks: Action &1 is not possible |
021 | You cannot create a subtask for task &1 |
022 | Task &1 has not been released: Actual data cannot be changed |
024 | Dates of mirrored task &1 were changed in the original task |
025 | Dates of mirrored task &1 were updated; save data |
026 | Duration of task is being adjusted - actual dates exist |
027 | Task assignment is not possible because it would create a loop |
028 | Task &1 is a mirrored task; confirmation not possible |
029 | Task type &1 has been deactivated and cannot be used |
030 | Cost/revenue rate for the task '&1' was reset |
031 | Overflow when adding up work of task '&1'; value &2 was set |
032 | Inconsistencies may occur when tasks w. percentage of compl. are exported |
033 | Error occurred during work conversion for the task '&1' |
034 | Error occurred during actual work conversion for the task '&1' |
035 | Error occurred during remaining work conversion for the task '&1' |
036 | Task type &2 is not valid for project type &1 |
037 | Task contains both object links and operative object links |
038 | This type of operative object link is not allowed |
039 | New engineering record created; save the project |
040 | Object links cannot be created |
041 | Changing status impossible; task &1 is relevant to approval |
042 | You cannot release milestone &1. A higher-level element is not released |
043 | Status &1 is not supported for milestones. |
044 | You cannot undo the completion of milestone &1. |
045 | You cannot release milestone &1. |
046 | You cannot complete milestone &1. |