DPR_TASK - Messages for Tasks

The following messages are stored in message class DPR_TASK: Messages for Tasks.
It is part of development package DEVELOPMENT_PROJECTS_TASK in software component PPM-PRO-STR. This development package consists of objects that can be grouped under "Project Management - Tasks".
Message Nr
Message Text
001Select a valid task type
002Select a valid unit
004You cannot change the task type because the task has been released
005You cannot change the obligatory indicator
006You cannot change the approval-relevant indicator
007You cannot change the process because the task has been released
011&1 &2 has not been completed
012Actual date is in the future
013Original task no longer exists for mirrored task &1
014Project &1 is already a subproject for a different master task
015'Relevant for Approval' indicator cannot be set for task &1
016Project type &1 does not allow subtasks to be created
017Subproject for task &1 no longer exists
018You do not have authorization for original task &1 for mirrored task &2
019Cannot change tasks: Action &1 is not possible
020Cannot change external tasks: Action &1 is not possible
021You cannot create a subtask for task &1
022Task &1 has not been released: Actual data cannot be changed
024Dates of mirrored task &1 were changed in the original task
025Dates of mirrored task &1 were updated; save data
026Duration of task is being adjusted - actual dates exist
027Task assignment is not possible because it would create a loop
028Task &1 is a mirrored task; confirmation not possible
029Task type &1 has been deactivated and cannot be used
030Cost/revenue rate for the task '&1' was reset
031Overflow when adding up work of task '&1'; value &2 was set
032Inconsistencies may occur when tasks w. percentage of compl. are exported
033Error occurred during work conversion for the task '&1'
034Error occurred during actual work conversion for the task '&1'
035Error occurred during remaining work conversion for the task '&1'
036Task type &2 is not valid for project type &1
037Task contains both object links and operative object links
038This type of operative object link is not allowed
039New engineering record created; save the project
040Object links cannot be created
041Changing status impossible; task &1 is relevant to approval
042You cannot release milestone &1. A higher-level element is not released
043Status &1 is not supported for milestones.
044You cannot undo the completion of milestone &1.
045You cannot release milestone &1.
046You cannot complete milestone &1.
Privacy Policy