PJ - MPX interface messages (Download and Upload)
The following messages are stored in message class PJ: MPX interface messages (Download and Upload).
It is part of development package CN_MPX_IF in software component PS-ST-INT. This development package consists of objects that can be grouped under "MPX Interface".
It is part of development package CN_MPX_IF in software component PS-ST-INT. This development package consists of objects that can be grouped under "MPX Interface".
Message Nr ▲ | Message Text |
|---|---|
| 000 | ===download=== |
| 010 | You cannot download all the factory calendars |
| 030 | Unit & not allowed (only time units allowed) |
| 040 | Internal error when reading calendar & |
| 050 | You cannot download all calendar exceptions |
| 060 | Internal error when determining a work center |
| 070 | The MPX interface is supported under Windows and OS/2 only |
| 080 | Standard network & alternative & does not exist |
| 090 | Key set at: & |
| 100 | No activities found. Nothing downloaded. |
| 101 | This transaction is no longer accessible through SAP GUI. |
| 120 | PC line too long: "& ...&" (longer than & characters) |
| 130 | Error when writing PC file (Please check PC) |
| 140 | Profile & does not exist |
| 150 | W: The PC filename was changed (Please confirm) |
| 160 | Standard network & & downloaded to file & |
| 170 | Please set finish date to a date later than the start date |
| 180 | W: This PC file already exists |
| 190 | MPX texts not maintained in the language for the PC program |
| 200 | This function is not supported under this operating system |
| 500 | ===upload=== |
| 510 | Not all standard network default values set: BDC may stop |
| 520 | Not all work center default values set: BDC may stop |
| 530 | PC file & not found or is empty |
| 540 | PC file & not in MPX format |
| 550 | Please correct the PC filename |
| 560 | No project label in & |
| 570 | Unit & not allowed here (only particular time units allowed) |
| 580 | Error in relationship: & (Please correct) |
| 590 | Relationship & is to an activity which does not exist |
| 600 | Relationship & to group of activities is not supported |
| 610 | Relationship & between different alternatives not permitted |
| 630 | Error when reading PC file (Please check PC) |
| 640 | Activity & assigned resource & is not defined (Please check) |
| 650 | Activity & defined twice (Please check) |
| 660 | Activity element & defined twice (Check your entry) |
| 670 | Work center & defined twice (Please check) |
| 680 | Relationship & defined twice (Please check) |
| 690 | Duration "&" is not in a valid MPX unit (Please correct) |
| 700 | PC file not found |
| 710 | Control key & not valid (Please check) |
| 720 | Milestone indicator & not valid (Please check) |
| 730 | Resource assignments to group of activities & not supported |
| 740 | W: Objects not entered could be referenced: BDC may stop |
| 750 | W: Resources not entered could be referenced: BDC may stop |
| 760 | Correct the time (format): & |
| 770 | Correct the date (format): & |
| 898 | Unforeseen error in routine & |
| 899 | & & & & & |