PLM_SE_PRS_MESSAGES - Message class for PS services

The following messages are stored in message class PLM_SE_PRS_MESSAGES: Message class for PS services.
It is part of development package PLM_SE_PRS_XI_PROXY in software component PS. This development package consists of objects that can be grouped under "Proxy implementations for Project System".
Message Nr
Message Text
000ChangeStateID could not be determined.
001No update possible, data has been changed since last read
002Mandatory field &1 not provided.
003Field &1 not found in table &2.
004Value &1 not found in table &2.
005&1 party ID is missing.
006The partner with ID &1 and role code &2 could not be read.
007Invalid action code for party.
008The required network ID is missing.
009Provide only one ID as network parent!
010Exactly one of ID or SenderTechnicalID has to be provided for activity &1
011The unit of measure for Free/Total Float Duration must be DAY!
012The content of &1 exceeds the field length of the target field.
013Invalid domain value: &1 in &2.
014Exactly one duration unit allowed.
015The partner &1 already exists.
016The partner &1 is not assigned to this project.
017WBS &1 already exists.
018WBS &1 does not exist.
019Milestone &1 already exists.
020Milestone &1 does not exist.
021Network &1 already exists.
022Network &1 does not exist.
023Only Customer/Vendor code values are permitted for Product Recipient.
024For action &1 the mandatory fields are missing.
025Activity &1 already exists.
026Activity &1 does not exist.
027No InternalID-TechnicalID correspondence found.
028Material component already assigned to the activity.
029Not assigned material component.
030Relationship already exists.
031Nonexistent relationship.
032Enter either SuccessorNetworkID or SuccessorNetworkSenderTechnicalID.
033Invalid value &1 for &2.
034NetworkRelationship: Predecessor network must be the parent network.
035NetworkRelationship: Predecessor activity must be the parent activity.
036The action on milestone &1 could not be performed.
037Exactly-once request cannot be locked: &1 (error code: &2).
038Exactly-once request timed out (message UUID &1).
039Internal error in exactly-once processing (message UUID &1).
040UUID &1 for element &2 does not comply to required pattern.
041Internal error storing response for request message UUID &1.
042Error in creating the network relationship.
043Error in changing the network relationship.
044Error in deleting the network relationship.
045Progress of WBS element &1 could be determined
046Enter Completion Percent below 100.
047Project Definition &1 could be changed successfully
048Project Definition &1 changed successfully.
049Progress of WBS element &1 could not be determined
050ISO code of system language could not be determined.
051Object number of project &1 could not be determined.
052Object number of wbs element &1 could not be determined.
053Object number of network &1 could not be determined.
054Object number of activity &1 &2 could not be determined.
055Object number of material component &1 could not be determined.
056Name for &1 &2 could not be determined.
057Field &1 is required.
058External unit of measurement &1 is not unique for language &2.
059Unit of measurement ISO code &1 is not supported.
060&1 conversion failed: No external code exists for internal code &2.
061Entry &1 in &2 does not exist in table &3.
062Value &1 in &2 is larger than &3.
063&1 has to be the same as &2.
064Individual measure units have to be the same as &1.
065Only customer and vendor are accepted in &1.
066Project &1 does not exist.
067&1 should be provided using unit &2.
068Creating the partner failed.
069There is a loop in the network hierarchy.
070&1 has to uniquely identify a WBS element.
071&1 has to uniquely identify a network.
072&1 has to uniquely identify an activity in a given network.
073Parent WBS element has to be the same for a network and its subnetworks.
074Parent WBS element has to be the same for an acty and its parent ntwk.
075Activity hierarchy can be at most one level deep.
076Parent WBS element has to be the same for an acty and its acty element.
077Parent network has to be the same for an acty and its acty element.
078&1
079&1 has to be between &2 and &3.
080Project ID &1 may not be used.
081WBS element ID &1 may not be used.
082Acty elements cannot have ntwk relations or milestones.
083A network cannot be its own parent.
084The ID of an acty elmnt must be different from the ID of its parent acty.
085Insufficient authorization on milestone &1
086For action &1 the mandatory fields &2 or &3 are missing.
087Insufficient authorization to create milestone
088System status &2 is active (WBS &1), Milestone cannot be &3
146Progress of Activity &1 could be determined
149Progress of Activity &1 could not be determined