DPR_DASHBOARD - Dashboard Data for Project
Dashboard Data for Project information is stored in SAP table DPR_DASHBOARD.
It is part of development package DEVELOPMENT_PROJECTS_EVE in software component PPM-PRO-EVA. This development package consists of objects that can be grouped under "Evaluations / Dashboard / Alerts".
It is part of development package DEVELOPMENT_PROJECTS_EVE in software component PPM-PRO-EVA. This development package consists of objects that can be grouped under "Evaluations / Dashboard / Alerts".
Fields for table DPR_DASHBOARD
Field Name | Description | Is Key | Data Element | Data Type | Length | Check Table |
---|---|---|---|---|---|---|
CLIENT | Client | X | MANDT | CLNT | 6 | |
OBJECT_GUID | Application Object GUID | X | EVE_TV_OBJECT_GUID | RAW | 16 | |
ROOT_OBJECT_GUID | Root Object GUID of an Application Hierarchy | EVE_TV_ROOT_OBJECT_GUID | RAW | 16 | ||
PARENT_GUID | GUID of Superior Object | EVE_TV_PARENT_OBJECT_GUID | RAW | 16 | ||
LAST_CHANGED_ON | UTC Time Stamp in Short Form (YYYYMMDDhhmmss)(with Con.Exit) | DPR_TV_TIMESTAMP | DEC | 8 | ||
OBJECT_TYPE | Object Category for Evaluation Engine | EVE_TV_OBJECT_TYPE | CHAR | 32 | ||
SEC_OBJECT_TYPE | Secondary Object Type for Evaluation Engine | EVE_TV_SEC_OBJECT_TYPE | CHAR | 32 | ||
.INCLUDE | DPR_TS_DASHBOARD_ATTR | 0 | ||||
PHASE_GUID | GUID of a Phase | EVE_TV_PHASE_GUID | RAW | 16 | ||
ACTUAL_FINISH | Actual Finish | DPR_TV_ACTUAL_FINISH | DATS | 16 | ||
ACTUAL_START | Actual Start | DPR_TV_ACTUAL_START | DATS | 16 | ||
DOC_TOTAL | Number of Documents | DPR_TV_DOCUMENTS_TOTAL | INT2 | 2 | ||
OBL_TOTAL | Number of Object Links | DPR_TV_OBJ_LINKS_TOTAL | INT2 | 2 | ||
COLL_TOTAL | Number of Collaborations | DPR_TV_COLLABORATIONS_TOTAL | INT2 | 2 | ||
CTRL_PLAN_TOTAL | Number of Control Plans | DPR_TV_CTRL_PLANS_TOTAL | INT2 | 2 | ||
SYSTEM_STATUS | System Status for an Object as a String | DPR_TV_SYSTEM_STATUS | STRG | 8 | ||
USER_STATUS | User Status for an Object | DPR_TV_USER_STATUS | STRG | 8 | ||
STATUS_SCHEME | Status Profile | J_STSMA | CHAR | 16 | * | |
RESPONSIBLES | Persons Responsible or Responsible Organizational Units | DPR_TV_PERSONS_RESPONSIBLE | STRG | 8 | ||
MAX_SEVERITY | Maximum Severity of a Threshold Value in the Evaluations | EVE_TV_MAX_THLD_SEVERITY | NUMC | 10 | * | |
MANUAL_SEVERITY | Manual Severity of a Threshold Value in the Evaluations | EVE_TV_MANUAL_THLD_SEVERITY | NUMC | 10 | * | |
AGGR_SEVERITY | Aggregated Severity of a Threshold Value in the Evaluation | EVE_TV_AGGR_THLD_SEVERITY | NUMC | 10 | * | |
PRIORITY | Priority | DPR_TV_PRIORITY | INT1 | 1 | ||
WORK_COMPLETE | Percentage of Completion of Project Work | DPR_TV_PRO_WORK_COMPLETE | NUMC | 6 | ||
PERFORM_START | Start Date of Project Met | DPR_TV_PERFORMANCE_START | CHAR | 2 | ||
PERFORM_FINISH | Finish Date of Project Met | DPR_TV_PERFORMANCE_FINISH | CHAR | 2 | ||
PERFORM_SCOPE | Scope of Project Met | DPR_TV_PERFORMANCE_SCOPE | NUMC | 6 | ||
PERFORM_SCHED | Tasks That Met Deadline | DPR_TV_PERFORMANCE_SCHEDULE | NUMC | 6 | ||
PROJECT_DELAY | Key Figure: Project Delay | DPR_TV_PROJECT_DELAY | INT2 | 2 | ||
STAFFING | Key Figure: Staffing Status | DPR_TV_STAFFING_INDICATOR | NUMC | 6 | ||
PLANNED_COSTS | Value of Planned Costs for a Project | DPR_TV_PLANNED_COSTS | CURR | 8 | ||
ACTUAL_COSTS | Value of Actual Costs of a Project | DPR_TV_ACTUAL_COSTS | CURR | 8 | ||
BUDGET | Budget Value of a Project | DPR_TV_BUDGET | CURR | 8 | ||
CURRENCY | Currency Key | WAERS | CUKY | 10 | * | |
RESULT_CLI | Result for Checklist Item | DPR_TV_CKLITEM_RESULT | CHAR | 2 | ||
MILESTONE | Milestone Indicator | DPR_TV_MILESTONE | CHAR | 2 | ||
GROUPING | Grouping | DPR_TV_GROUPING | CHAR | 80 | ||
PRO_TYPE | Project Type | DPR_TV_PRO_TYPE | CHAR | 30 | ||
PHA_TYPE | Phase Type | DPR_TV_PHA_TYPE | CHAR | 30 | * | |
TSK_TYPE | Task Type | DPR_TV_TSK_TYPE | CHAR | 30 | * | |
CLH_TYPE | Checklist Type | DPR_TV_CLH_TYPE | CHAR | 30 | * | |
SEARCH_FIELD | Search Field | DPR_TV_SEARCH_FIELD | CHAR | 80 | ||
PROCESS | Process | DPR_TV_PROCESS | CHAR | 30 | * | |
APP_RELEVANT | Relevant for Approval | DPR_TV_APPROVAL_RELEVANT | CHAR | 2 | ||
OBLIGATORY | Mandatory | DPR_TV_OBLIGATORY | CHAR | 2 | ||
PC_GROUP | Group for Project Charter | DPR_TV_PC_GROUP | CHAR | 30 | * | |
PC_SAV_TARGET | Savings Target | DPR_TV_PC_SAV_TARGET | INT4 | 4 | ||
PC_SAV_CURR | Savings Actual | DPR_TV_PC_SAV_CURRENT | INT4 | 4 | ||
PC_SAV_CRCY | Savings Currency | DPR_TV_PC_SAV_CURRENCY | CUKY | 10 | * | |
PC_ROI_TARGET | ROI Target | DPR_TV_PC_ROI_TARGET | INT4 | 4 | ||
PC_ROI_CURR | ROI Actual | DPR_TV_PC_ROI_CURRENT | INT4 | 4 | ||
PC_ROI_CRCY | ROI Currency | DPR_TV_PC_ROI_CURRENCY | CUKY | 10 | * | |
PC_SIG_BASE | Base Value Six Sigma | DPR_TV_PC_SIGMA_BASE | INT4 | 4 | ||
PC_SIG_TARG | Target Value Six Sigma | DPR_TV_PC_SIGMA_TARGET | INT4 | 4 | ||
PC_SIG_CURR | Current/Final Value Six Sigma | DPR_TV_PC_SIGMA_CURRENT | INT4 | 4 |